08/28/2023    Initial notification of an odor in the water
08/28/2023    Flushed hydrants and tested for chlorine residuals
09/29/2023    Flushed hydrants
10/02/2023     Water samples collected and sent to Maryland Spectral Services (a private 
                       independent lab) for analysis
01/31/2024     Flushed hydrants
02/05/2024      Weather warmed up enough to start Pressure Testing the system for leaks
02/12/2024     Collected water samples and tested
02/20/2024     Flushed hydrants
02/27/2024     Maryland Rural Water onsite sounding for leaks
03/01/2024      Flushed hydrants
03/06/2024      Pressure testing completed for Shallmar Road, East Main, West Main, and 
                      Center streets. Seven valves in other parts of the town failed and were 
                      ordered for repairs.
03/20/2024     Samples collected again at multiple locations including inside some homes
03/28/2024     Maryland Rural Water onsite sounding for leaks
04/15/2024     Test results received and confirm no contaminants
04/22/2024     MDE received test results and update on what work has been completed 
                       and the plan to proceed.
05/08/2024      Valves and supplies needed for repairs are onsite.
05/22/2024    Contractors scheduled to start valve replacement first week of June
06/10/2024    Contractors repaired two valves State Street
06/20/2024    Contractors repaired three valves at the corner of Willow and State streets.
06/21/2024    Commissioners informed of the issues with Kitzmiller water
06/24/2024    Commissioners held public meeting in Kitzmiller and heard concerns from 
                      residents directly
06/25/2024    Valve repaired on Homestead Street
06/26/2024    Completed pressure testing North of Rt 38
07/01/2024      Pressure testing resumes south of Rt38
07/02/2024      Pressure testing continues south of Rt 38
07/03/2024      Large leak located and repaired on Race Street
07/08/2024      Pressure testing South of Rt 38 and the East Main Street area.
07/10/2024     Valve repaired on Third Street and pressure testing completed 
                      south of Rt 38
07/10/2024     Bacteria Samples Collected by MES = Negative Results
07/12/2024     Alley H line leak repairs have been completed
07/24/2024     Started receiving complaints in new areas, flushed entire town
Collected well samples and water samples at the school for a full analysis, results received 8/4/2024 forwarded to MDE and MES
08/06/2024     Flushed water from water tower at night
08/07/2024     Flushed water from water tower at night, samples taken in morning
08/08/2024     Flushed water from water tower at night, samples taken in morning
08/09/2024     Flushed water from water tower at night, samples taken in morning
08/12/2024     Flushed water from water tower at night, samples taken in morning
08/13/2024     Flushed water from water tower at night, samples taken in morning
08/14/2024     Flushed water from water tower at night, samples taken in morning
08/15/2024     Water trucked to Community Center for disbursement for affected residents
08/16/2024     County Commissioners met with the Secretary of MDE to apprise her of the situation and ask for assistance
08/20/2024     The Director of Garrett County Utilities and staff visited the Kitzmiller plant and residences to check on progress and issues related to the problem
08/21/2024     Second truck of water sent to Community Center for disbursement for affected residents
08/21/2024     Flushing Shallmar and Peewee extensions
08/12/2024    Investigating potential filtration systems, quotes, sampling point modifications, etc
12/05/2024    A plan has been submitted to MDE to install a filtration system at the pump station.
12/18/2024        The proposed water filtration system has been approved by MDE. The filtration system has been ordered and prep work has been started at the water treatment facility. Following receiving all the materials, an installation period is anticipated to be 30-45 days.
01/27/2025     County staff attends Kitzmiller Town Meeting
01/29/2025     Concrete was poured for new filter base
01/30/2025      Electrical upgrades are being installed
03/04/2025     The majority of the equipment is onsite, and installation has started. Water system infrastructure piping is scheduled to be completed on 3/21. Testing and sample monitoring will follow with plans to be in full operation prior to 3/28.
04/15/2025     Kitzmiller water treatment upgrades and system flushing have been completed. Regular service maintenance schedules for hot water tank flushing should be performed following the tank manufactures recommendations.